ningke / tasksched

HackerRank's Task Scheduling Problem

Geek Repo:Geek Repo

Github PK Tool:Github PK Tool

tasksched

HackerRank's Task Scheduling Problem

This is a problem from hackerrank:

You have a long list of tasks that you need to do today. Task i is specified by the deadline by which you have to complete it (Di) and the number of minutes it will take you to complete the task (Mi). You need not complete a task at a stretch. You can complete a part of it, switch to another task and then switch back.

You've realized that it might not actually be possible complete all the tasks by their deadline, so you have decided to complete them so that the maximum amount by which a task's completion time overshoots its deadline is minimized.

Input: The first line contains the number of tasks T. Each of the next T lines contains two integers Di and Mi.

Output: Output T lines. The ith line should contain the minimum maximum overshoot you can obtain by optimally scheduling the first i tasks on your list. See the sample input for clarification.

Constraints: 1 <= T <= 100000 1 <= Di <= 100000 1 <= Mi <= 1000

Sample Input: 5 2 2 1 1 4 3 10 1 2 1

Sample Output: 0 1 2 2 3

Solution

The key insight is that the task with a later deadline MUST be completed later than a task with an earlier deadline - regardless how you break up the tasks. Otherwise, the first task (the one with an earlier deadline) will overshoot its own deadline by more than the second task overshoots its deadline. So we can essentially just sort the tasks by their deadline and complete them in that order. The problem description about breaking up tasks are just there to confuse you. (why?)

However, since the problem requires you to do this incrementally, i.e., solve the scheduling for tasks from 1 to n. The naive method above takes O(nlog(n)) for each iteration, so it will take O((n^2)log(n)) in total, which is unacceptable: a solution in Python only has 16 seconds to solve the problem. So a more efficient solution is needed. This is turns out to be quite hard.

The key difficulty is that when inserting a new task, all tasks that follows the newly inserted task must have their completion time (and overtime) updated. That is the part that causes the O(n^2) behavior. It turns out that there is a data structure to do this efficiently, it is called a Binary Indexed Tree. Secondly, we also need to keep track of the max overtime for three ranges, the tasks before the new tasks, the new task itself, and tasks after the new task. This problem is known as the "range-minimum-query" and a data structure called Segment Tree.

Files:

tasksched.py: Naive implemention that sorts data every round.

tasksched_fast.py: Fast implemention using Binary Indexed Tree and Segment Tree.

tasksched_hackrank.py: Optimized Python (Removed small functions and lambdas).

tasksched_tester.py: Generates test cases.

bitree.py: Binary Indexed Tree.

segtree.py: Segment Tree.