Telecom Case Study

Problem statement

This project serves as a telecom case study, showcasing the implementation of an ETL (Extract, Transform, Load) process. Using SQL Server Integration Services (SSIS). The processed data is then loaded into a Data Warehouse (DWH) designed and created using SQL Server Management Studio. This project demonstrates the end-to-end ETL pipeline for telecom data, ensuring data quality and error handeling.

Source System Overview and Life-Cycle

Signalling data describes the subscriber network activities and interaction. Subscriber does an event such as call, rowsing, latching, SMS, etc. The network vendor collects the subscriber data in real-time and bulk every 5 min activity in one fill and push it to landing servers.

4G Signaling Data

Created by Moustafa Mahmoud

The dataset is generated using a script and it does not describe the full telecom dataset for signalling but it simulates the general idea.

DataFormat

This section describes the input data and its format.

Column Data Type Length Is Nullable Sample
ID Int False 156
IMSI String 9 False 310120265
IMEI String 14 True 490154203237518
CELL Int False 123
LAC Int False 12
EVENT_TYPE String 1 True 1
EVENT_TS Timestamp False 16/1/2020 7:45:43

The required processing must be completed on this data before storing it in the data warehouse. The processing steps are as follows:

Column Name Mapping Rules Target Model
ID As-is Transaction_id
IMSI As-is, reject the record if null IMSI
IMSI Join with IMSI reference and get subscriber id, add -99999 if null subscriber_id
IMEI Substring first 8 chars, if null or size is less than 15 add -99999 TAC
IMEI Substring last 6 chars, if null or size is less than 15 add -99999 SNR
IMEI As-is IMEI
CELL As-is, reject the record if null CELL
LAC As-is, reject the record if null LAC
EVENT_TYPE As-is EVENT_TYPE
EVENT_TS Validate the timestamp format to be YYYY-MM-DD HH:MM:SS, reject the record if null EVENT_TS

Rejected records will be stored in a separate table, and the original CSV file name will be recorded.

During the data recording process in the database, there is some additional information that needs to be recorded in the auditing table to ensure the quality of the data storage:

  • The number of records in the CSV file.
  • The number of records successfully stored in the database.
  • The number of rejected records due to not meeting the required conditions.
  • Linking the data stored in the database with the original CSV file.

After completing the data storage process in the database according to the aforementioned conditions, Archive the CSV files to another folder.

Project Phases:

  1. Extract Data from CSV files.
  2. Process and transfer data.
  3. Deal with data that does not meet the quality requirements, such as Nulls and missing values.
  4. Error Handling.
  5. Archive files that have been processed and transferred.
  6. Auditing the processed data.

Screenshots

In this section, you can find screenshots of the different stages of the ETL process, showcasing key stages, including data flow, successful control flow execution, and data loading into the Data Warehouse (DWH).

Data Flow

Data Flow

Control Flow

Control Flow

Sample of loaded data

Data Warehouse