Design review R6: better schedule
caseyjlaw opened this issue · comments
Casey Law commented
R6: A more granular schedule, with definite targets should be developed to track progress. This schedule shall be shared with affected aspects of NRAO to avoid priority collisions.
- Schedule needs to be integrated with other NRAO activities and priorities:
- Identify periods of conflict for key personnel
- More granular schedule for early identification of slippage
Casey Law commented
White boarded refinement of a 6-8month plan at https://drive.google.com/file/d/0B7Md1PdoX8jodkh4S1U5amwzdE0.
Sequence of targets of software, correlator room development, cluster purchasing plan, and early science in late 2017.