Primavera Import Fails on WBS Processing.
amarkssmartpm opened this issue · comments
If no activities under a WBS entry contain an actual start date the process will fail when calculating the duration. In my case there is one activity which is a finish milestone. This type of milestone does not contain a actual start date.
I added a code change for this on my fork, amarkssmartpm/mpxj.
Would you be able to add a sample file here, or to the PR, to replicate the issue. It'll save me some time constructing something appropriate - thanks!
@amarkssmartpm unfortunately I think the sample file may have been stripped off during the email->GitHub comment translation. Would you be able to post it here directly? Thanks!
Attached the zip file with the xml.
Thank you! I've merged your change.