frePPLe / frepple

frePPLe - open source supply chain planning

Home Page:https://frepple.com

Geek Repo:Geek Repo

Github PK Tool:Github PK Tool

Operation.EffectiveEnd is ignored

petrakozielova opened this issue · comments

Hello,
I have a problem with Operation.EffectiveEnd field. I have routing operation with suboperations. One of the suboperations has EffectiveEnd on 1980-01-01 00:01:00, so it can't be planned. However, the Demand on Item produced by routing operation is planned on time. So the effective end is being ignored in this case. In case I change Effective End of the routing to 1980-01-01 00:01:00, the Demand is not planned as I expected. It seems that in case of suboperations, the effective end is not used, only the routing operation's is.
Routing_operation_disabled.xlsx

This is expected behavior. We have no plans to change that.

Leaving this ticket open in case this functionality is needed for others.

Thank you for quick response.